ROTATION
Each pool is built
in the order that it is dug. This means that if your pool is dug on the 3rd day
and your neighbor’s pool is dug on the 8th, then the all crews would go first
to your pool then to the neighbor’s. This is called “rotation”. In
addition to a pool’s construction rotating within our company, we often are
subject to rotation within a subcontractor’s schedule.

WEATHER DELAYS
Even if it doesn't’t
rain at your house, rain at another location may delay a crew from finishing
their work in progress. This in turn holds up the rotation to your house even
though you experienced no rain at all! Certain phases are more effected by wet
weather than others. Grading for concrete decking and access for machinery to
dig or cleanup is held up by wet ground. It is pretty hard to find someone
who’ll work in the middle of a steel rebar cage during a lightening storm.
Plaster can’t be applied in the rain and concrete and gunite cannot be applied
below certain temperatures (normally 35 degrees).
UTILITY MARKING
We will have your
utilities marked prior to excavation. All utilities in the easement will be
marked and some will even be marked where they cross your yard. We do not ever
ramp in the easement. You may want to move your pool to avoid these lines during
layout. It is important to remember that we are not responsible for any
underground utilities, including but not limited to, electric, cable, gas,
sprinkler, drainage, or phone lines unless specifically included in your
contract in writing.
PRE-CONSTRUCTION MEETING
You will be given
this booklet as part of your construction package. We go over everything in this
package so that we’re on the same page during construction. Your construction
package will include: one Lakeside Custom Pools & Spas, LLC. Construction
Information booklet; one copy of your contract: any contract addendum; one copy
of your sales drawing; one construction drawing: plus any other pertinent data.
We will normally layout the pool at this meeting for your approval and signoff.
We will put up caution tape if required. We normally place a yard sign out
with your approval. It is at this time that we will post (in a plastic sheeting)
several sets of plans, permits, etc.
YOU’VE GOT TO BREAK A FEW
EGGS TO MAKE AN OMELET
Remember that this
is major construction going on in your back yard. Your yard is going to be a
mess for most of your pool’s construction. We normally do a major cleanup
after your deck is poured, so bear with us while we build your pool as fast as
possible. Try to keep in mind the beautiful pool you’ll have when it’s
finished.
ACCESS
It’s impossible to
build your pool without getting into your back yard. Sometimes this is easy and
sometimes it’s very difficult. Your designer should have discussed access with
you and it will definitely be discussed at your pre-construction meeting. You and
your designer have predetermined the degree of restoration of this access area.
We will at the very least regrade with sand where ruts were made.
EXCAVATION
Most dirt digs are
done with a bobcat and most rock digs are done with a backhoe with an attachment
for rock breaking. Your pool’s layout is normally to water’s edge so it’s
necessary for your excavator to move his forms back one foot for the bond beam.
It will normally be
necessary to use a ramp for the excavation. The standard rule is two feet out
for every foot of excavation. So, if the pool is six feet deep, then the ramp
would extend outside of the water’s edge about twelve feet. This is important
to keep in mind when considering underground utilities.
Your excavator will
dig out a twelve-inch by twelve-inch box beam and a 6” wall and floor. Three
inches will be added to the excavated floor depth to compensate for the exposed
portion of your pool tile. So, if your pool should finish 4’6” then your
digger will dig to 5’3” below the pool’s wooden forms.
GAS AND SEWER
Your heater will
normally run off of natural gas or propane. The heater must be hooked up to the
source of this gas and run to your equipment. If your gas is to be inspected,
the installer will put a gauge on the end of the line closest to the equipment.
This will be removed after inspection. Sewer reroutes must have a certain number
of clean outs above ground to meet code. If these are high, don’t worry; they
will be cut down lower later on. If they are located in the deck area, then a
cap will be inserted flush with the decking to hide the clean out. Sewer
reroutes cannot involve ninety-degree angles but must be entirely made up of
forty-five degree angles to make the turns required.
GUNITE
Your shell is shot
with genuine gunite. Your bond beam should finish at a minimum of 12” x 12”,
your walls and floor at a minimum 6”.
Your steps (and
normally benches) are solid gunite. No steel is needed unless these structures
are located at a depth of 5’ or more.
Your crew will leave
deck dowels extending above the pool’s form boards. These are for securing
electrical bond wire and can be bent down after gunite to help support the deck.
These will have plastic caps attached for your safety.
POOL PLUMBING
Your pool is simply
a circulation system. Water is pulled from the skimmer and main drain to your
pool pump’s suction side
and pushed through your pool’s returns by your
pump’s return side. Some of this return water may also go to waterfalls, etc.
Your pool skimmer
helps clean the top 3” of water by “skimming” the debris from the
water’s surface. Your drain helps with overall pool circulation and
sanitation. Your pool may have a fill line for filling and/or an overflow line.
Many people in the southwest will forgo an overflow line because of our area’s
constant evaporation. They let the pool fill up and then drop back to a normal
level on its own. This keeps them from adding as much water to the pool. You
will see pipes extending from your pool skimmers during construction. These
allow us to put the plumbing system under pressure to insure there are no leaks.
The return pipes are stubbed past the gunite and capped during construction. These will be cut and fittings attached at plaster.
You will notice
holes in the bottom of and sometimes the sides of your gunite pool. These are
weep holes to prevent your pool from floating due to subsurface water pressure.
They will be covered up at the time of plaster. IF you don’t see umbrella
sleeves or volleyball cups don’t worry, we’ll do them prior to plaster. You
should try to water down your gunite shell beginning the day after your gunite
is complete. This will insure that your gunite does not cure too fast. Once or
twice a day should be sufficient—just getting the surface wet. Please don’t
walk (Or allow pets on) on freshly shot gunite——it may look hard but it’s
better to wait overnight. Excess gunite (or rebound) will be placed in the
pool’s ramp or hauled off at cleanup.
TILE AND COPING
Your coping normally
covers the bond beam. It varies in thickness from l”-3” depending on the
type used. No color is normally added to the mortar but we will add color to
your tile’s mortar at a small cost if you so desire. Directly below the coping
is your 6” tile line. Your pool’s water level should be maintained at the
middle of this tile line.
If you have chosen
accent tile for your pool, it will often be applied now, but may also be applied
just before plaster. You can add this tile trim at any time prior to plaster and
it’s normally put on steps and benches.
ELECTRIC
You will require
electricity to run your pump, light and if present, your heater. The first step
in this phase is trenching for the conduit. After the path is trenched, a gray
conduit or pipe is laid. This conduit is a gray color so that everyone knows
it’s electric and avoids digging or cutting into it. This conduit may be run
to a junction box in an effort to save you money on electrical. Our electrician
will also run a bond wire from your steel rebar deck dowels, pool and or spa
light, and any metal, including hand rails or ladders.
Our electrician
will then pull wires through the conduit and connect your equipment and lights
to your breaker box. If your box is inside your home or a locked garage, you
will need to make yourself available to let the electrician inside. Our electrician will hook up a time clock that will control your pump and filter
operation. He will also provide a switch for your light. An outlet will also be
provided at your equipment location that is a “ground fault interrupter”. We
will need between 25 and 60 amps for your equipment. If your service is full,
then you may need a sub panel added. There will be an additional cost for this
and our electrician will notify us if one is needed. Your pool and spa lights
are water-cooled and cannot be operated while not under water. Please do not
turn on your breakers or any switches prior to our starting your full pool. The
plaster crew normally will actually install the lights into the wall, so don’t
be worried if you see a light on your pools bottom with the cord hanging loose.
DECKING
Your decking phase
begins with forming. This will often entail digging dirt out or bringing sand or
dirt in to achieve the finished elevation. After your deck has been brought to
the correct grade, your crew will add #3(318”) steel rebar on 18” centers
and tie this into your previously discussed deck dowels. If piers or footings
are necessary, they will be added at this time. Your plumbing pipes are kept
under pressure during this forming to insure that there are no leaks later under
the deck.
There are numerous
types of deck materials. You have obviously worked with your designer to get
your preferred deck that fits into your pool budget. The thickness of your deck
will vary from 4” to 6”. If you have chosen a topping type deck (flagstone,
brick. Americoat, or kool deck) then a sub deck will be needed. This sub deck is
made of brushed concrete. If you’ve chosen hand seeded pea gravel, then the
rainbow pea gravel will be seeded on top of the concrete and become a part of
the finished product.
If you’ve chosen
Americoat, it will be necessary to wait a few days after the sub deck is poured
and then treat the surface. After treatment the crew will return to add color to
your deck. Pea gravel will need to be acid washed after a week or so to remove
the concrete film that is present. We will do whatever is necessary to drain
your deck of any rainwater. We are not responsible for drainage problems in your
yard away from your decking and but will address these problems at the time of
decking for an additional cost if you bring them to our attention. Your designer
may have already worked with you on correcting any problems.
CLEAN UP
We will perform a
final cleanup prior to plaster. All form boards, tile and coping debris, excess
gunite; dirt, etc. will be hauled away at that time. We will also fill in any
ruts left by the construction crews, grade out with sand 3’ around your
decking, and prepare (prep) your pool for plaster. The degree of restoration is
already determined by you and your designer prior to clean up and will be
discussed at your pre-construction meeting.
FENCE UP
If we had to remove
your fence we will put it backup unless other arrangements have been made. This
will normally be done prior to plaster.
LANDSCAPE
If you have included
landscape as part of your contract, we will do this work prior to plaster unless
other arrangements have been made.
PLASTER PREP
Your plaster must be
prepared prior to applying plaster. This involves cleaning out the debris,
pumping out any water, and scraping the sides.
PLASTER
Your plaster coat
actually is what seals the pool and allows it to retain water. We will not be
able to plaster your pool if it is “weeping” water. We will notify you
immediately if this is the case. If you have chosen colored plaster there are
going to be streaks and imperfections. It is inherent in the color process and
cannot be avoided. Once your pool is plastered we will immediately put a hose in
the pool (with a rag attached) to begin filling your pool. Do not turn the water
off for any reason until your pool’s water level reaches the middle of your
pool tile! Once your pool is filled you should begin brushing it down at least
once a day. We will provide you with a pole and brush. Brushing the pool down
will make your pool’s plaster surface smoother, so you should concentrate on
the areas that you will walk on , sit on , etc.
POOL START-UP
After your pool is
filled with water to the middle of the tile line, call us and we’ll come out
and start up your pool. A pool start up consists of cuffing out your skimmer
loops (used to pressurize your plumbing), installing directional inlets, turning
on your motors (to begin circulation), bleeding your gas line (if required),
adding start up chemicals to your pool, and testing all aspects of the pool. He
will drop off a pole and brush at this time so that you may begin brushing your
pool. He will not normally install your pool cleaner because it may damage the
new plaster.
POOL SCHOOL
At “pool
school”, we teach you how to maintain and operate your pool. It is a good idea
to video tape this process. He will also provide you with an “Operation’s
Manual”. We will mark your pipes so that you know how your particular pool
operates. Just remember that pipes are either
on the suction or
return side ,so you should just imagine a large circle with your pump and filter
at the center. We normally wait a few days after your pool’s start up before
we schedule pool school. This allows your pool’s water to stabilize so we can
teach you how to balance your water.
WARRANTY
Your pool’s
warranty begins after it is started up. All workmanship is warranted for one
year. Other warranties are from one year to lifetime depending on the problem.
All Hayward equipment carries a three year parts and labor warranty. Americoat
decking carries a five-year warranty. Your pool’s structure is warranted to
hold water forever. You will be given a list of warranties at pool school.
|